Board of Trustees Board Meetings Board Policies
Calendars Complaints/Public Input Contact Us Directory District Boundary Maps Feature Articles Features Archive Local Control News Nondiscrimination Policy Organizational Beliefs Press Releases Publications School Accountability Reports School Plans
Business Services Enrollment & Residency Food Services Human Resources Maintenance & Operations Teaching & Learning Technology Services
High School Campuses College Now Concurrent Enrollment Middle College Adult & Community Education Summer School 2014
Annual Notifications Course Information and Graduation Requirements College & Career Planning Community Advisory Committee Community Links English Learners PTA Council Resources for Parents Resources for Students Special Services Translation Help
Bond Program Citizens' Oversight Committee PIP History of FUHSD Bonds
LHS Sports Fields Improvements Project Construction
Print Main Column

Construction Status and Plans Forecast *

 

Phase 1 – Construction of New Stober Field and Main Field and Track

Phase 2 – Construction of Softball and Baseball Fields

 

Week Starting

Major Completed / Planned Activities Noise Impact Traffic Impact
Nov 12, 2012
  • Phase 1
    •  
  • Phase 2
    • Continue caulking and sealing
    • Continue installation of temporary outfield fences
    • Continue fabrication and installation of dugout downspout
    • Continue rock and asphalt composition of fire access road and basketball area
    • Continue installation of perimeter fences / gates
    • Continue installation of signage
Low
to
Medium
Medium
Nov 19, 2012
  • Phase 1
    •  
  • Phase 2
    • Continue installation of temporary outfield fences
    • Continue fabrication and installation of dugout downspout
    • Continue installation of perimeter fences / gates
    • Continue installation of signage
    • Start installation of basketball standards
    • Start mulch at fire access lane
Low
to
Medium
Medium
Nov 26, 2012
  • Phase 1
    •  
  • Phase 2
    • Continue installation of perimeter fences / gates
    • Continue installation of signage
    • Installation of miscellaneous railings / handrails
    • Miscellaneous painting
    • AC overcoat
    • Asphalt striping
Low
to
Medium
Medium

 

* Construction plans, including without limitation sequencing, start dates, durations and completion date, are subject to change without notice or obligation.  The information posted on this page is accurate as of the time it was posted but is not guaranteed to be accurate thereafter.  The information on this page will be updated at least weekly, usually on Friday afternoons.  If up to the minute information is needed, please call Sharon Serrano at 408.522.2203 during normal working hours.